A Copperbelt operator brought us six hydraulic ram cylinders pulled from underground load-haul-dump machines after repeated seal failures were causing unplanned downtime. Two units had visible barrel scoring from contaminated fluid, and all six were past due for a full teardown.
All six cylinders were returned within the two-week window agreed at handover, ahead of the fleet's scheduled maintenance slot. None of the rebuilt units have returned for seal-related failure in the twelve months since.
Client: Copperbelt mining operation (name withheld)
Date: March 2026
Service area: Mining, Hydraulics